Set NA to Summary Fields?

M

MichaelA

Would anyone know if it is possible to set summary date and duration
fields to NA so that they don't show rolled up data?


Thanks and regards
Michael A.
 
J

John

MichaelA said:
Would anyone know if it is possible to set summary date and duration
fields to NA so that they don't show rolled up data?


Thanks and regards
Michael A.

Michael,
Simple answer. No.

The whole point of a summary line is to summarize parameters of the
performance tasks below it.

John
Project MVP
 
J

Jan De Messemaeker

Hi Michael,

As such, No.
You could create three custom fields (say duration1=Duration, Start1=Start
and finish1=Finish) and not roll these up to summary tasks, then show them
in your view instead of the real stuff.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availabliy check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top