Murray Potts
I wish to setup two resource calenders; one for a 12 hour day shift and one
for a 12 hour night shift. The site works 24/7 and resources work 12 hours
per day, 6:00 to 6:00, 14 days on 7 day off. This is very typical for mining
in Western Australia where staff fly in fly out. the problem is entering a
shift that starts at 06:00PM on one day and finishes at 06:00AM the next day.
MS Project informs that the finish time must be later then the start time.
for a 12 hour night shift. The site works 24/7 and resources work 12 hours
per day, 6:00 to 6:00, 14 days on 7 day off. This is very typical for mining
in Western Australia where staff fly in fly out. the problem is entering a
shift that starts at 06:00PM on one day and finishes at 06:00AM the next day.
MS Project informs that the finish time must be later then the start time.