Normal schedule - 8 hrs per day/5 days per week/weekends off. I need to have
an event happen 45 calendar days after a start date. For example: start on
7-1-07, due on 8-15-07. I tried "45 days", resulting in a due date of 8-31.
Tried "1.5 Months" and that gave a due date of 8-10.

Is there an abbreviation used in Predecessors that will change the timing
for this task to Calendar Days?

Thanks,
Mike R.
 
M

Mike Glen

Hi Mike,

Welcome to this Microsoft Project newsgroup :)

Yes, put an e in front to make it elapsed time eg 45 edays.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
M

Mike R.

Jan & Mike,
That's the answer!! I didn't remember "e" for "elaspsed" days!!