A
alper
I am currently trying to conduct a manufacturing plan for the electrical
panels production phase in our manufacturing department. Up to now, we have
planned our manufacturing schedule with using ms office excel. so as you can
predict that our system is not as complex as any other production planning
system in which has been using with the big plants to monitor and run their
production schedule smoothly. our production panel planning based on coming
orders irregularly from our customers and also each order for the panels
completely different from each other. therefore purshasing the materials,
scheduling to finish dates and resource allocation(workers) between the
projects make the planning production system almost not applicable to any
other uniqe production planning software for our planning purpose! I belive
also with using ms project does not exactly fulfill our most optimizing goal
to monitor best planning stradegy. I would like to give you briefly
explaining our production phases within the multiple projects, tasks and
subtasks. In my project, there are some multiple projects like project A,
project B, project C……, also each project has some subtasks (we are producing
electrical panels, so in project A there are several panels to be produced.
Also each panel has 3 production phase. 1 purchasing the materials 2
manufacturing the panel 3 logistics. So we only just want to know how many
workers we should assign into manufacturing stage and how we should
balance(assign) the workers into each panel to produce and also within the
projects. Our total number of workers are 20. we do not want to know that
assigning number of workers for stage 1 (purchasing the materials ) and stage
3 logistics. Manufacturing stage is the only one primary target to focus on.
But we also would like to see the other phases (1,3) in our forecast plan.(
in ms project 2003 regarding each project’s finish dates and their date
links(slack and lags) ).to just want keep the relationships between each
panel and its subtasks also between projects…
ms project schedule style gives us a enough flexibility to schedule and
monitor manufacturing phase more efficiently with regards to leveling
overalocations among the multiple projects which get start at the same time.
lastly, we do not spare extra budget for buying a new costly software. I
also believe strongly with using ms project as a planning tool in our system
provides partly monitoring and scheduling the panels more efficiently than
before(excel).
I need your kindly advise and any comments which are useful for me to coduct
the ms project into my manufacturing planing set up.
Question 1. if I choose the check the effort driven box in manufacturing
stage for each panel task and also uncheck the effort driven box for the
other 2 stages (1,3) for each panel task, it can be the solution to keep
focusing on assigning worker for only manufacturing stages in each panel and
giving 0 value( decimal) to max units in stages (1,3) to be able to see
finish dates of panels( and also project ).
Question 2. in my case using the resource pool is the best way to handle
this whole project?
On the other hand, if there are 7 projects and each project has 5 to 10
panels how can I see and run those projects and their panels (also their
stages) as one sheet in ms project 2003
question 3. how can I use critical path method to adjust and level
workers(resource allocation) in multiple projects get going at the
manufacturing site.
(we only control over manufacturing process(phase 2)
but also phase1 and phase 3 should be on the ms project plan in order keep
the whole integrity strong enough to monitor project finish dates.
Is there any alternative way to run this whole project other than using
resource pool method????
my e-mail addres: (e-mail address removed)
alper
thanks
panels production phase in our manufacturing department. Up to now, we have
planned our manufacturing schedule with using ms office excel. so as you can
predict that our system is not as complex as any other production planning
system in which has been using with the big plants to monitor and run their
production schedule smoothly. our production panel planning based on coming
orders irregularly from our customers and also each order for the panels
completely different from each other. therefore purshasing the materials,
scheduling to finish dates and resource allocation(workers) between the
projects make the planning production system almost not applicable to any
other uniqe production planning software for our planning purpose! I belive
also with using ms project does not exactly fulfill our most optimizing goal
to monitor best planning stradegy. I would like to give you briefly
explaining our production phases within the multiple projects, tasks and
subtasks. In my project, there are some multiple projects like project A,
project B, project C……, also each project has some subtasks (we are producing
electrical panels, so in project A there are several panels to be produced.
Also each panel has 3 production phase. 1 purchasing the materials 2
manufacturing the panel 3 logistics. So we only just want to know how many
workers we should assign into manufacturing stage and how we should
balance(assign) the workers into each panel to produce and also within the
projects. Our total number of workers are 20. we do not want to know that
assigning number of workers for stage 1 (purchasing the materials ) and stage
3 logistics. Manufacturing stage is the only one primary target to focus on.
But we also would like to see the other phases (1,3) in our forecast plan.(
in ms project 2003 regarding each project’s finish dates and their date
links(slack and lags) ).to just want keep the relationships between each
panel and its subtasks also between projects…
ms project schedule style gives us a enough flexibility to schedule and
monitor manufacturing phase more efficiently with regards to leveling
overalocations among the multiple projects which get start at the same time.
lastly, we do not spare extra budget for buying a new costly software. I
also believe strongly with using ms project as a planning tool in our system
provides partly monitoring and scheduling the panels more efficiently than
before(excel).
I need your kindly advise and any comments which are useful for me to coduct
the ms project into my manufacturing planing set up.
Question 1. if I choose the check the effort driven box in manufacturing
stage for each panel task and also uncheck the effort driven box for the
other 2 stages (1,3) for each panel task, it can be the solution to keep
focusing on assigning worker for only manufacturing stages in each panel and
giving 0 value( decimal) to max units in stages (1,3) to be able to see
finish dates of panels( and also project ).
Question 2. in my case using the resource pool is the best way to handle
this whole project?
On the other hand, if there are 7 projects and each project has 5 to 10
panels how can I see and run those projects and their panels (also their
stages) as one sheet in ms project 2003
question 3. how can I use critical path method to adjust and level
workers(resource allocation) in multiple projects get going at the
manufacturing site.
(we only control over manufacturing process(phase 2)
but also phase1 and phase 3 should be on the ms project plan in order keep
the whole integrity strong enough to monitor project finish dates.
Is there any alternative way to run this whole project other than using
resource pool method????
my e-mail addres: (e-mail address removed)
alper
thanks