Setting a work resource as "Level of Effort"

J

jt

I am trying to load tasks/resources into my schedule that are level of
effort. These include things like recurring meetings that will happen 1 hour
per week from one milestone to another. For example:

Task Review 1 (milestone, 0d): 1/1/10
Task Review 2 (milestone, 0d): 1/1/11

I want to set Task A to start at Review 1 (1/1/10) and finish at Review 2
(1/1/11) with a resource of 1 hour per week (so, 52 hours). But, if Review 2
gets pushed out to 1/1/12, then the task should stretch to end on 1/1/12 with
1 hour per week (now, 104 hours). Similarly, if Review 1 gets pushed out to
7/1/10 but Review 2 doesn't move, then the task would shorten (still 1 hour
per week) to 26 hours.

I was able to get this to work by copying the review dates and
paste-special-paste link into the start and finish dates of Task A and
setting fixed units to 2.5%. That works, but the links are not very stable.

Is there a better way of doing accomplishing the same result?

Thanks,
J
 
J

JulieS

Hello J,

It sounds as though you've created Task A as a hammock task which is
what I would recommend. No other alternative that I know of.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top