Setting default duration to seconds

W

whcinc

Is there a way to set the default duration to seconds? The smallest unit on the Options>Schedule tab is minutes.

Thank you.

PS: Right now I am pretending minutes are seconds. That seems just so kludgy.
 
R

Rod Gill

Hi,

Minutes is the smallest unit of time in Project. What are you scheduling?

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
whcinc said:
Is there a way to set the default duration to seconds? The smallest unit
on the Options>Schedule tab is minutes.
Thank you.

PS: Right now I am pretending minutes are seconds. That seems just so
kludgy.
 