C
chris togeretz
Good day! I'm hoping that you can help me figure something out - half
an hour googling and in my "MS Project for Dummies" book doesn't give
me even a hint!
Let's say we have this project:
1. Project
1.1 Task 1 (2 days)
1.2 Task 2 (3 days)
and if Task 2 must be completed after Task 1 is done (FS link) then
the project has a duration of 5 days.
Now. Say you want to squeeze this project into 3 days. Task 1 then is
"allowed" to take only 2*(3/5) = 1.2 days, and Task 2 is allowed to
take 3*(3/5) = 1.8 days.
Is there a way I can specify "work units" (e.g. "2" for Task 1 and "3"
for Task 2) so that I can set their "allowable" durations simply by
changing the overall project length?
Thanks for your help!
Chris
an hour googling and in my "MS Project for Dummies" book doesn't give
me even a hint!
Let's say we have this project:
1. Project
1.1 Task 1 (2 days)
1.2 Task 2 (3 days)
and if Task 2 must be completed after Task 1 is done (FS link) then
the project has a duration of 5 days.
Now. Say you want to squeeze this project into 3 days. Task 1 then is
"allowed" to take only 2*(3/5) = 1.2 days, and Task 2 is allowed to
take 3*(3/5) = 1.8 days.
Is there a way I can specify "work units" (e.g. "2" for Task 1 and "3"
for Task 2) so that I can set their "allowable" durations simply by
changing the overall project length?
Thanks for your help!
Chris