Hi,
I'm MS Project novice. I'm trying to make a new task to my MS Project
file. When I set a start day 15.2.2010 and duration 40, I get an end
date thursday 8.4.2010. I was thinking it should produce for the end
date friday 9.4.2010? There is 40 working days (mon-fri) between those
days (15.2.-9.4.2010). Am I missing something?
I'm MS Project novice. I'm trying to make a new task to my MS Project
file. When I set a start day 15.2.2010 and duration 40, I get an end
date thursday 8.4.2010. I was thinking it should produce for the end
date friday 9.4.2010? There is 40 working days (mon-fri) between those
days (15.2.-9.4.2010). Am I missing something?