Rhonda
I have tried a number of ways to accomplish the following:
Our work times are 8:00 - 5:00 (8hrs per day M-F).
Resource availabilty is 6 hrs per day. I have tried
setting global calendars so that all projects use the same
company standard calendar with the above times. I set the
hours per day to 6, week to 30, months to 20.
When enterprise resources are assigned to tasks they are
being scheduled (allocated) 8 hrs per day.
How do I set the global calendar so that my resources are
only scheduled for 6 hours a day. i.e. If I have a task
that is 40 hrs of work, with 1 assigned resource, I would
expect the duration to be 6 days.
Also, how to I ensure each project is using the global
company calendar.
Can someone clarify this for me?
Thanks, Rhonda
Our work times are 8:00 - 5:00 (8hrs per day M-F).
Resource availabilty is 6 hrs per day. I have tried
setting global calendars so that all projects use the same
company standard calendar with the above times. I set the
hours per day to 6, week to 30, months to 20.
When enterprise resources are assigned to tasks they are
being scheduled (allocated) 8 hrs per day.
How do I set the global calendar so that my resources are
only scheduled for 6 hours a day. i.e. If I have a task
that is 40 hrs of work, with 1 assigned resource, I would
expect the duration to be 6 days.
Also, how to I ensure each project is using the global
company calendar.
Can someone clarify this for me?
Thanks, Rhonda