R
Rich
I am trying to set the start date of certain tasks is my project as
two calandar days since the task previous was finished. This is to
allow me two days for material delivery. I have been setting the
presecessor for task 4 as 3FD+2 days. This works fine if the person
completing the job is an 8 hour employee. However when I assign task
4 which takes 2 hours to a specialty employee that only works 3 hours
a day the 2 day lag seems to push the start day out 16 hours of this
guys work day or 5 or so days.. How can I set the lag based on
calandar days or based on a differnt schedule then the person that is
doing the work? I guess I could set up a milestone or a really short
task to take delivery of materials and force that task to use the 8
hour a day calandar instead of the workers calandar but I was trying
to cut down the numnber of tasks since the delivery of material is
really almost a zero minute event.
two calandar days since the task previous was finished. This is to
allow me two days for material delivery. I have been setting the
presecessor for task 4 as 3FD+2 days. This works fine if the person
completing the job is an 8 hour employee. However when I assign task
4 which takes 2 hours to a specialty employee that only works 3 hours
a day the 2 day lag seems to push the start day out 16 hours of this
guys work day or 5 or so days.. How can I set the lag based on
calandar days or based on a differnt schedule then the person that is
doing the work? I guess I could set up a milestone or a really short
task to take delivery of materials and force that task to use the 8
hour a day calandar instead of the workers calandar but I was trying
to cut down the numnber of tasks since the delivery of material is
really almost a zero minute event.