dee
Hi..
I'm dee, I want to ask bout this problem :
if we assign one resource to 2 task, for example :
task A : with duration (20-23July)
task B : with duration (23-24July)
if he divides max unit (unit availabilty) = 50% for task A, and 50% for task
B, what should I do?
I have set the max unit in view - resource usage - resource information
and set the resource availability :
available from available to units
20July 22Jul 100%
23Jul 23Jul 50%
24Jul 100%
But, it doesn't affect the work for 23July (the total work is still 16 hourse)
Thank u for u help
regards,
dee
I'm dee, I want to ask bout this problem :
if we assign one resource to 2 task, for example :
task A : with duration (20-23July)
task B : with duration (23-24July)
if he divides max unit (unit availabilty) = 50% for task A, and 50% for task
B, what should I do?
I have set the max unit in view - resource usage - resource information
and set the resource availability :
available from available to units
20July 22Jul 100%
23Jul 23Jul 50%
24Jul 100%
But, it doesn't affect the work for 23July (the total work is still 16 hourse)
Thank u for u help
regards,
dee