N
nickc
O.K. I must be overlooking something simple. I planned the project up to
July with the original baseline. I have added additional tasks taking me
out several months, and would like to set a new baseline for those new tasks.
I went to tools tracking - set baseline- baseline 1 -selected tasks and
nothing happened. Still shows NA, did not take the start/finish dates and
move them to baseline. I then tried this for the entire project (baseline 1)
and still no change. Any ideas where I'm going wrong?
July with the original baseline. I have added additional tasks taking me
out several months, and would like to set a new baseline for those new tasks.
I went to tools tracking - set baseline- baseline 1 -selected tasks and
nothing happened. Still shows NA, did not take the start/finish dates and
move them to baseline. I then tried this for the entire project (baseline 1)
and still no change. Any ideas where I'm going wrong?