Hi there,
Can someone please help me with the following:
In MS project 2007, I am currently trying to set weekend days as overtime.
Basically I've already set my calendar to use only week days, and when I
change it and set the project to run on weekends (normal 8 hour days) it does
not show any values for overtime worked.
When I go to the Resource Usage page and set 'overtime work' hours then the
program just extends the working hours on weekdays (so from an 8 hour day it
moves to, say, 12 hours). Ive tried setting each individual task as 'Fixed
Duration' under task type (task information box) to no avail.
What I need is to keep my week days at 8 hours and cause the setting of
overtime hours to extend onto the weekend thereby shortening the total task
time.
So really I'd like to set saturday and sunday as overtime and the rest of
the week days as normal rates.
Is there anyone who can help me with this? Im sorry if this sounds a bit
confusing, as I am clearly confused myself!
Can someone please help me with the following:
In MS project 2007, I am currently trying to set weekend days as overtime.
Basically I've already set my calendar to use only week days, and when I
change it and set the project to run on weekends (normal 8 hour days) it does
not show any values for overtime worked.
When I go to the Resource Usage page and set 'overtime work' hours then the
program just extends the working hours on weekdays (so from an 8 hour day it
moves to, say, 12 hours). Ive tried setting each individual task as 'Fixed
Duration' under task type (task information box) to no avail.
What I need is to keep my week days at 8 hours and cause the setting of
overtime hours to extend onto the weekend thereby shortening the total task
time.
So really I'd like to set saturday and sunday as overtime and the rest of
the week days as normal rates.
Is there anyone who can help me with this? Im sorry if this sounds a bit
confusing, as I am clearly confused myself!