R
rfreschner
I have a Task (Task 3) that I would like to start 5 days after Task 1 ends
and end 5 days after Task 2 ends (ex. Task 1 ends on 3/30 and Task 2 ends on
4/20, I would like Task 3 to start on 4/6 and end on 4/27). I thought I
would be able to do this by setting a FS+5 predecessor on Task 1 and a FF+5
predecessor on Task 2, but that doesn't seem to work. The only way to
accomplish it seems to be to adjust the duration until I get the dates (or
close to them) that I want. Is there a way to have the dates automatically
set this way without setting the task duration or effort?
and end 5 days after Task 2 ends (ex. Task 1 ends on 3/30 and Task 2 ends on
4/20, I would like Task 3 to start on 4/6 and end on 4/27). I thought I
would be able to do this by setting a FS+5 predecessor on Task 1 and a FF+5
predecessor on Task 2, but that doesn't seem to work. The only way to
accomplish it seems to be to adjust the duration until I get the dates (or
close to them) that I want. Is there a way to have the dates automatically
set this way without setting the task duration or effort?