R
Richard Spooner
I need to set the duration of an ASAP task (which has predecessors and
successors) to a minimum of three complete working days. I can't see how to
do it!
The requirement is for an external review process. Examples, assuming a
Mon - Fri, 8 am - 5 pm calendar:
1. If the review task could start at noon on Mon, the finish time should be
5 pm on Thu (allowing three complete days of Tue, Wed, and Thu - the extra
five hours on Mon is a bonus!)
2. If the task could start at 8 am Fri, the finish time should be 5 pm Tue
(Fri, Mon, Tue provided for).
3. If the task could start at 8.01 am Fri, the finish time should be 5 pm
Wed (Mon, Tue and Wed provided for - extra time on Fri is a bonus.)
I cannot set absolute dates as constraints, as I need to move the start date
as the planning and implementation occurs. I am using Project 2003 Standard.
Thanks in advance for your help.
successors) to a minimum of three complete working days. I can't see how to
do it!
The requirement is for an external review process. Examples, assuming a
Mon - Fri, 8 am - 5 pm calendar:
1. If the review task could start at noon on Mon, the finish time should be
5 pm on Thu (allowing three complete days of Tue, Wed, and Thu - the extra
five hours on Mon is a bonus!)
2. If the task could start at 8 am Fri, the finish time should be 5 pm Tue
(Fri, Mon, Tue provided for).
3. If the task could start at 8.01 am Fri, the finish time should be 5 pm
Wed (Mon, Tue and Wed provided for - extra time on Fri is a bonus.)
I cannot set absolute dates as constraints, as I need to move the start date
as the planning and implementation occurs. I am using Project 2003 Standard.
Thanks in advance for your help.