setting task starting time by hour?

A

andy colb

I have a weekend project that starts on Friday night and
finishes Monday morning.
How do I tell Project 2000 to start a task at a specific
time (say 8 pm) on a specific date (say august 6), but not
at 8 am (which is the native start time)? The start/finish
format doesn't seem to have an obvious way to designate
specific times to start or finish.

Thanks in advance for any advice.

Andy
 
J

Jan De Messemaeker

Hi Andy,

Maybe it doesn't seem to have but it has.
You can enter any time as 8/8/4 08:09 Project will accept it.
To visualize it Go to Tools, Options, View, for date Format select one that
has time of day.
HTH
 
J

Jamie Hart

Andy,

Go to Tools, then Change Working Time. Select any day that is NOT a working
day for your project (Mon-Thur) and click Nonworking Time. On the working
days select the time frame you want in From and TO areas.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top