You can select the 4 days at a time in the calendar. Simply click
and drag the 4 days on, set your working time. Click and drag the 4
days off, set as non-working. Repeat.
I am guessing you have two shifts of *people* - day shift and night
shift. For an example of a "night shift" which spans midnight
(12:00 am), take a look at the "Third Shift" calendar included with
Project.
I suggest creating two calendars -- one for Day shift and one for
Night shift. Then assign the correct calendar to the specific
resource. When you assign a person to a task, the task schedule
will shift to correspond with the calendar assigned to the resource.
Julie
Ask a Question
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.