P
Problem setting actual start dates
I have a project where I have start and finish dates defined (to say,
5/15/2006 and 5/16/2006). Now I want to define actual start date to say,
6/14/2006). When I go to the task and specify an Actual Start date of
6/14/2006, it also changes the Start date to 6/14/2006 (and the Finish date
to 6/15/2006). this is driving me nuts.....
5/15/2006 and 5/16/2006). Now I want to define actual start date to say,
6/14/2006). When I go to the task and specify an Actual Start date of
6/14/2006, it also changes the Start date to 6/14/2006 (and the Finish date
to 6/15/2006). this is driving me nuts.....