P
ProjectUser
I could use some best practice advice for the following scenario (using
Project 2003):
I need to track project costs and do Earned Value. Part of the challenge is
that we don’t track resources and probably won’t at this stage. So, I’ve
added a Cost WBS with a cost milestone task. I thought I could enter the
budgeted amount under “fixed cost†for each of the cost milestone tasks
(we’re doing multiple construction sites as one complete project.) Also,
this schedule will be inserted into another schedule.
Some of the unexpectant results I’m seeing:
• Complete project costs (all milestone task fixed costs) don’t roll to the
top of the schedule; particularly, the master schedule
• When adding actuals, the actuals get added, not subtracted, to the total
cost…?
There are other unexpectant results I’m seeing that would lengthen this.
The bottom line: how do I best set this schedule so that I enter budgeted
amounts, then track actuals, and have all the fields needed to do Earned
Value Analysis (of course, once I baseline this schedule)?
Thanks!
Project 2003):
I need to track project costs and do Earned Value. Part of the challenge is
that we don’t track resources and probably won’t at this stage. So, I’ve
added a Cost WBS with a cost milestone task. I thought I could enter the
budgeted amount under “fixed cost†for each of the cost milestone tasks
(we’re doing multiple construction sites as one complete project.) Also,
this schedule will be inserted into another schedule.
Some of the unexpectant results I’m seeing:
• Complete project costs (all milestone task fixed costs) don’t roll to the
top of the schedule; particularly, the master schedule
• When adding actuals, the actuals get added, not subtracted, to the total
cost…?
There are other unexpectant results I’m seeing that would lengthen this.
The bottom line: how do I best set this schedule so that I enter budgeted
amounts, then track actuals, and have all the fields needed to do Earned
Value Analysis (of course, once I baseline this schedule)?
Thanks!