Hi everyone,
I checked the mvps.org FAQ and read a couple of posts about this and
since english is not my first language, I would like to know if I
understood correctly how to use the feature of creating custom
calendars.
When I create a New Project, I assign this project a "Standard
Calendar" that fits every ressources. (meaning, everything related to
the company itself)
Then, I create a custom calendar for every ressources regarding their
special requirements or location in the world.
For example, if my company is in Canada, my project standard calendar
should contain all related events in my company that will affect my
project (company events, national holidays). Then, if my ressources
are canadians, I can assign them the standard calendar.
For my USA ressources, I would need to create a custom calendar and
assign it to them. Then these resources would follow the US calendar,
right?
Then, since I base my project on Canadian National holidays, will my
project prevent US resources to be assigned during the canadian
thanksgiving days (since it is different in Canada)?
Stefan
I checked the mvps.org FAQ and read a couple of posts about this and
since english is not my first language, I would like to know if I
understood correctly how to use the feature of creating custom
calendars.
When I create a New Project, I assign this project a "Standard
Calendar" that fits every ressources. (meaning, everything related to
the company itself)
Then, I create a custom calendar for every ressources regarding their
special requirements or location in the world.
For example, if my company is in Canada, my project standard calendar
should contain all related events in my company that will affect my
project (company events, national holidays). Then, if my ressources
are canadians, I can assign them the standard calendar.
For my USA ressources, I would need to create a custom calendar and
assign it to them. Then these resources would follow the US calendar,
right?
Then, since I base my project on Canadian National holidays, will my
project prevent US resources to be assigned during the canadian
thanksgiving days (since it is different in Canada)?
Stefan