K
KT
Hi,
The scenario is, I am creating a base template in which there is an activity
- 'Initial Meeting', with time duration of 2 hrs. During this activity there
involves a set of tasks that needs to be accomplished which do not have
specific time duration. But in Microsoft project, I am not able to set the
timeline for Initial Meeting as 2 hrs, since there are sub-tasks associated
with it having an option to set the timeline (which I don't have) instead. Is
there any other way to accomplish this? Also I have some other tasks that
don’t have timeline for example: "Refer client for training"; so when I enter
the duration as '0 Days', there appears the Milestone symbol in the Gantt
chart. Am I doing any mistake?!! Is there any other better way to do it so
that I don't get a milestone symbol there?!!! I am not sure whether I am
clear in my questions.....If you don't understand I will try to come up with
different examples...I really appreciate your help in advance.
Thanks
KT
The scenario is, I am creating a base template in which there is an activity
- 'Initial Meeting', with time duration of 2 hrs. During this activity there
involves a set of tasks that needs to be accomplished which do not have
specific time duration. But in Microsoft project, I am not able to set the
timeline for Initial Meeting as 2 hrs, since there are sub-tasks associated
with it having an option to set the timeline (which I don't have) instead. Is
there any other way to accomplish this? Also I have some other tasks that
don’t have timeline for example: "Refer client for training"; so when I enter
the duration as '0 Days', there appears the Milestone symbol in the Gantt
chart. Am I doing any mistake?!! Is there any other better way to do it so
that I don't get a milestone symbol there?!!! I am not sure whether I am
clear in my questions.....If you don't understand I will try to come up with
different examples...I really appreciate your help in advance.
Thanks
KT