Haris
Hi,
I've defined a couple of custom fields, like 'Activity Description' for
resources to detail what they're working on in their time sheets. While using
this field in my project, i'd selected customize - published fields and
selected the custom fields. in the 'settings for activity description' i see
the radio button as disabled and set to 'Task' due to which for one task
which is assigned to 2 resources, whatever description one resource writes
and gets its updated by PM, appears on the other resource's time sheet.
What i think is that the setting should be 'Assignment' for the solution,
the again the feature is greyed out so can't try. This feature doesn't appear
as enabled for any of the custom outline codes.
I would appreciate if some one could guide me as to what am i missing.
Regards,
Haris
I've defined a couple of custom fields, like 'Activity Description' for
resources to detail what they're working on in their time sheets. While using
this field in my project, i'd selected customize - published fields and
selected the custom fields. in the 'settings for activity description' i see
the radio button as disabled and set to 'Task' due to which for one task
which is assigned to 2 resources, whatever description one resource writes
and gets its updated by PM, appears on the other resource's time sheet.
What i think is that the setting should be 'Assignment' for the solution,
the again the feature is greyed out so can't try. This feature doesn't appear
as enabled for any of the custom outline codes.
I would appreciate if some one could guide me as to what am i missing.
Regards,
Haris