G
Guest
Hello:
I am having a problem with my shared calendar. I have a
server 2003 environment, and use Outlook 2003. When I
enter an event into from the main scheduling PC, it adds
them as all day events (which is what I want as the
default). However, when I view them from on of the other
PC's, it does not view them as all day events. It
schedules a time for them. And at times, because the start
time and end time are the same, it will span two days.
Long story short, how can I view the items as all day
events, the way they were entered. It is a local setting?
Thanks
I am having a problem with my shared calendar. I have a
server 2003 environment, and use Outlook 2003. When I
enter an event into from the main scheduling PC, it adds
them as all day events (which is what I want as the
default). However, when I view them from on of the other
PC's, it does not view them as all day events. It
schedules a time for them. And at times, because the start
time and end time are the same, it will span two days.
Long story short, how can I view the items as all day
events, the way they were entered. It is a local setting?
Thanks