K
Kristin
I teach MS Project basics (among other MS applications)
and had some questions in my class today that I am hoping
someone can help me with. Thanks in advance.
1. One of my students wants to be able to track the
changes that she makes to her project plan...and to get as
detailed as entering reasons why she has made those
changes. Any suggestions?
2. Is there a way for the project manager to define tasks
as "critical" (different from using Project's definition
of critical)? Even if is is color coding specific tasks?
3. How can I track "extra" costs incurred during the
project? For instance, I have a task in my project to set
up a cash register system in my store. I hire an outside
company to come in and do this. When they come, the
register is not there yet. They charge me a fee just for
showing up. Yet the task is not yet complete and they will
still charge me the original cost when they come back to
do the work. Where can I track this.
Thanks!
Kristin
and had some questions in my class today that I am hoping
someone can help me with. Thanks in advance.
1. One of my students wants to be able to track the
changes that she makes to her project plan...and to get as
detailed as entering reasons why she has made those
changes. Any suggestions?
2. Is there a way for the project manager to define tasks
as "critical" (different from using Project's definition
of critical)? Even if is is color coding specific tasks?
3. How can I track "extra" costs incurred during the
project? For instance, I have a task in my project to set
up a cash register system in my store. I hire an outside
company to come in and do this. When they come, the
register is not there yet. They charge me a fee just for
showing up. Yet the task is not yet complete and they will
still charge me the original cost when they come back to
do the work. Where can I track this.
Thanks!
Kristin