shared tasks are not appearing in my tasks view

S

Satya

Hi,
I'm using Project Server 2007. When I assign two resources to a task, the
task is not getting displayed in my tasks veiw for any of the resources.
Tasks are getting displayed only when there is single owner. did any of you
come across this behavior.
Regds
Satya
 
M

Marc Soester [MVP]

Hi Satya,

Can you check that the assignment owner for all resources are them selfs
please. If not, please make sure that each resource is their own assignment
owner. This will more then likely resolve the issue.
Let me know if it worked
Thanks
Marc
 