S
S St. John
Hello,
I have one timeline that deals with two projects, that are highly
interdependent on each other and share big portions of the same tasks.
One of the project, however, is a collaboration. I only want to maintain one
timeline - what's the best way to share the timeline. I know that I can
create a view with only their tasks, but what's to keep them from changing
views? Is there a way to lock it? They would like to see the Gantt, and not a
pdf.
We are using MSP 2003, standard.
Any thoughts would be greatly appreciated!
Thanks,
Shahera
I have one timeline that deals with two projects, that are highly
interdependent on each other and share big portions of the same tasks.
One of the project, however, is a collaboration. I only want to maintain one
timeline - what's the best way to share the timeline. I know that I can
create a view with only their tasks, but what's to keep them from changing
views? Is there a way to lock it? They would like to see the Gantt, and not a
pdf.
We are using MSP 2003, standard.
Any thoughts would be greatly appreciated!
Thanks,
Shahera