M
MartinR
Sorry to re-post this but it seems like a simple question
and a fairly straightforward bit of functionality that I'd
have though Project Server could do standing on its head.
Posted it a month ago and have had no replies.
In project server 2003 is their any way to set the
proportion of an individual resource allocated to a
specific project. i.e. to put 40% of a resource into
project A and 60% into project B without the project
manager having to set the percentages on a task by task
basis, therefore allowing him to view a resource's
availability within his own project's allowance
Thanks in advance
Martin
and a fairly straightforward bit of functionality that I'd
have though Project Server could do standing on its head.
Posted it a month ago and have had no replies.
In project server 2003 is their any way to set the
proportion of an individual resource allocated to a
specific project. i.e. to put 40% of a resource into
project A and 60% into project B without the project
manager having to set the percentages on a task by task
basis, therefore allowing him to view a resource's
availability within his own project's allowance
Thanks in advance
Martin