Ok, I've created a resource pool. I have asked several projects to share
resources with this pool. This works fine and is an excellent tool for
workload forecasting. However, When you open the resource pool MSP 2000
creates a Master Project. I have saved this Master Project but on opening the
resouce pool again another Master Project is created.
I want to be able to keep this Master Project and have it, Sub Projects and
Resource Pool that all open together. The reason for wanting to keep the
Master Project is that we have created a Template with numerous fields that
we use to export for Earned Value, ETC and Financial reporting.
 
M

Mike Glen

Hi Andy,

Welcome to this Microsoft Project newsgroup :)

The answer it to not open the pool at all, but open the mater project that
you have saved.

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #17 Multiple Projects, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top