M
Mauro
How can I check if a resource I want to assign an activity is already used
in another project in the same days?
We have a Project Server 2003 and use Project professional 2003.
If I open Organization Resource Pool, open some resources, and select
Resourse Usage, there are only blank fields and the "work" column is set to
0h for all the resources, even if they are already used (importing them from
project server) in many projects.
We actually save projects as .mpp files. Can this be an hint to solve the
problem?
Is there a way to be promted for a warning when I try to assing work to a
resource who is already assigned in the same days (in the same project or in
a different one)?
Thanks!!
Mauro
in another project in the same days?
We have a Project Server 2003 and use Project professional 2003.
If I open Organization Resource Pool, open some resources, and select
Resourse Usage, there are only blank fields and the "work" column is set to
0h for all the resources, even if they are already used (importing them from
project server) in many projects.
We actually save projects as .mpp files. Can this be an hint to solve the
problem?
Is there a way to be promted for a warning when I try to assing work to a
resource who is already assigned in the same days (in the same project or in
a different one)?
Thanks!!
Mauro