J
John
I have a task that has a total duration of 4 weeks. However, the resource
that is assigned is not going to work on the task for 4 weeks. Instead, she
will spend 2 hours within that four week period to accomplish the task. How
do I reflect this? Do I need to change the task type or whether it is
effort driven? Overall how do I show this in Project Pro?
Thanks
that is assigned is not going to work on the task for 4 weeks. Instead, she
will spend 2 hours within that four week period to accomplish the task. How
do I reflect this? Do I need to change the task type or whether it is
effort driven? Overall how do I show this in Project Pro?
Thanks