B
BUD1888
I have a spreadsheet that distributes hours between departments and across
the period of performance. Is there an easy way to make the hours shift if
the period of performance changes so I don't have to manually make the
change, i.e. the original start date is 01/01/2009 (9 months to complete) and
now it has shifted to 04/01/2009, but still 9 months to complete.
Example:
01/09 02/09 03/09, etc.
100 5 5 5
101 5 5 5
102 5 5 5
103 5 5 5
Any help with a formula would be great!! Thanks.
the period of performance. Is there an easy way to make the hours shift if
the period of performance changes so I don't have to manually make the
change, i.e. the original start date is 01/01/2009 (9 months to complete) and
now it has shifted to 04/01/2009, but still 9 months to complete.
Example:
01/09 02/09 03/09, etc.
100 5 5 5
101 5 5 5
102 5 5 5
103 5 5 5
Any help with a formula would be great!! Thanks.