R
Robin Roe
Hi
I am just wondering if anyone has a solution for the following scenario.
Task A has a duration of 5 days, Monday to Friday, Resource A and Resource B
are assigned
Resource A does not enter any actual hours for Monday but enters hours for
the Tuesday. PM accepts these hours onto the plan. The plan is now
rescheduled to start on Tuesday and is 5 days duration, which is to be
expected.
Resource B fills their timesheet after the PM has already accepted hours
from Resource A. Resource B fills hours as per plan for Monday and Tuesday.
PM Accepts these hours. The task now starts on Monday again (as expected) but
the Task is now 6 days duration instead of 5 with Resource B’s hours divided
evenly over the remaining 4 days rather than 3.
Is there a way to keep the task set in a predefined time frame. I don’t want
the schedule to change just because a resource didn’t enter time against the
first day of the task.
Thanks in advance
I am just wondering if anyone has a solution for the following scenario.
Task A has a duration of 5 days, Monday to Friday, Resource A and Resource B
are assigned
Resource A does not enter any actual hours for Monday but enters hours for
the Tuesday. PM accepts these hours onto the plan. The plan is now
rescheduled to start on Tuesday and is 5 days duration, which is to be
expected.
Resource B fills their timesheet after the PM has already accepted hours
from Resource A. Resource B fills hours as per plan for Monday and Tuesday.
PM Accepts these hours. The task now starts on Monday again (as expected) but
the Task is now 6 days duration instead of 5 with Resource B’s hours divided
evenly over the remaining 4 days rather than 3.
Is there a way to keep the task set in a predefined time frame. I don’t want
the schedule to change just because a resource didn’t enter time against the
first day of the task.
Thanks in advance