Short term projects

M

Michelle Hotz

We have a group in IT that works on customized solutions where typically the
projects last anywhere from 1 hr to at the most 3 days. We want to
standardize on everyone in IT using PWA PS2007 for timesheet entry. Any
thoughts on the best way to handle this group? We don't want to create
Project Pro projects for each one of their projects as that would often times
take longer than the actual project. Any feedback would be much appreciated.

Michelle
 
R

Roland

Michelle,

The folks sound to be production support related. I am presuming these
folks spend considerable time working on customized solutions. You can
create an LOE type task or tasks which are assigned specific IT resources. As
such, you can enter an estimated amount of work (4-8 hrs per day) for them
over a longer duration of time.

Roland
 