Yes, if you can't find anything else to link a task to, link it to the
"project finished" milestone.
Generally there are only two items in the schedule that do not have both a
predecessor and a successor. These are the "Authority to Proceed" milestone
and the "Project Compelte" milestone. Other than summary tasks, every detail
task should (and I said should not requires) both a predecessor and a
successor.
There is a paper about this on my blog. See the white paper on
"Predecessors and Successor Relationships"
Sometimes this "Program Complete" milestone gets a little over run with
predecessors. Some of these predecessors are important, others are level of
effort. What we do is create another milestone that we call "Garbage
Collection" and we use this as a successor to all the unimportant tasks in
the schedule like "Submit Activity Report - Sept 2009" ... The successor to
that would be "Garbage Collection". The successor to "Garbage Collection" is
"Program Complete"
This will help separate things out and give you a little less stress when
you try to find which of the 80 predecessors to "Program Complete" is driving
your program finish date.
--
If this post was helpful, please consider rating it.
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com