L
Lynn
Hi, I am trying to produce a report that will tell me which tasks have not
started that should have, and how many days late they are (in other words,
how many days behind schedule is the project).
The Should have started Report picks out the correct tasks (those that
should have started) but doesn't tell me how many days late they are.
I've tried lots of different tables in this report using entry, variance,
work, % complete but none give me the number of days (I expected it to be
variance).
I can work it out myself (at the moment as I only have 2 tasks which have
slipped) but surely that's what this report should be giving me?
I'd really appreciate some help. Thanks
started that should have, and how many days late they are (in other words,
how many days behind schedule is the project).
The Should have started Report picks out the correct tasks (those that
should have started) but doesn't tell me how many days late they are.
I've tried lots of different tables in this report using entry, variance,
work, % complete but none give me the number of days (I expected it to be
variance).
I can work it out myself (at the moment as I only have 2 tasks which have
slipped) but surely that's what this report should be giving me?
I'd really appreciate some help. Thanks