J
JeremyE
Almost all of my tasks are just ball park guesses as to how long they will take. For example, I have a task "Database Schema Design" that I guessed would take 31 hours and sure enough it only took 15 hours to complete. At this point to track my progress and I am going into the Task Sheet and entering "Actual Work" for that task. Then I go to the Gantt Chart/Work View and set the remaining work to zero which automatically sets the % complete to 100 %. But did I make the mistake of not setting ALL of my durations to estimated? I wasn't clear on when estimated durations should be used when I created the project plan, and I think that was a mistake. Could anyone give me some guidance? I can easily change all the durations to estimated, but I want to make sure that is what I should be doing.
Thank you so much!
Thank you so much!