RPage@SF said:
By using the Summary would each of the three phases be on their own line, or
would they all be on the same line? I need to have them all on the same line,
so as to save space. The split task function is a pain, I agree. Thanks for
your suggestion.
RPage@SF,
When created, the three education phases will be on three separate
lines, however if you collapse the summary lines (i.e. student names)
and set up the bar styles as detailed below, you will be able to see
each phase on the student name (i.e. summary) line.
First you will need to go to Format/Bar Styles and create a new set of
bars - first delete all existing bar styles. Create one new bar for each
educational phase. The easiest way to do that is to set the "show
for..." criteria as: FlagX,rolled up,not summary (where X = 1, 2 or 3)
for each bar respectively. Then go to Project/Task Information/General
tab and set each bar to "roll up Gantt bar to summary".
That should give what you want.
John
Project MVP