R
Randy Bristol
I would like to be able to enter a Budget value on each task and have that
budget figure sum at each rollup level. This I have accomplished with the
Number1 field.
Next I would like to enter an Actual value on selected task rollup rows and
then have a formula column that displays a Variance (rolled up budget figure
minus entered actual figure for the row) in a third numeric column. The
third numeric column should display no value (or zeroes) for all rows that do
not have a budget value entered.
My ultimate goal is to produce a report that shows budget figures for all
tasks and rolled up but actual and variance figures only for selected roll up
tasks since we track and report actuals at a higher level than we budget.
Can this be done in Project 2007? If so, how?
budget figure sum at each rollup level. This I have accomplished with the
Number1 field.
Next I would like to enter an Actual value on selected task rollup rows and
then have a formula column that displays a Variance (rolled up budget figure
minus entered actual figure for the row) in a third numeric column. The
third numeric column should display no value (or zeroes) for all rows that do
not have a budget value entered.
My ultimate goal is to produce a report that shows budget figures for all
tasks and rolled up but actual and variance figures only for selected roll up
tasks since we track and report actuals at a higher level than we budget.
Can this be done in Project 2007? If so, how?