Hello Sherif,
Just to add to the merriment...
It's not clear to me whether you really want your resources to work 7
days a week or if you just want to show the difference between the
finish date and start date of a task in "calendar" days.
Both Richard and "Redneck David" have given you good directions on how
to change the project calendar to a 7-day per week schedule and Steve
has pointed out that generally when referring to duration in Project
we are referring to working days.
Non-the-less, if you wish to leave the calendars alone, you can create
a calculated field that will show the number of calendar days
(including Saturday and Sundays) between the start and finish. Add a
spare duration field (Duration1 for example) to your task table.
Customize the field (right click in the column heading and choose
customize) and click the formula button. In the formula box enter the
following formula:
DateDiff("d",[Start],[Finish])*[Minutes Per Day]
The duration1 column will now show the number of days between the
start and finish dates of each task.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project