I change the Enterprise Task Text1 to Task ID and insert to my Project. I
select Published Fields in Tool > Customize and select Task ID for
publishing to Web. On PWA, I allow the Enterprise Task Text1 showed in
Timesheet View. But when I select Timesheet View, the column name of
Enterprise Task Text1 is not right (not Task ID), it show predefined column
name: Baseline Start, sometime it show Baseline Finish etc.
How to fix it?
Thanks
I change the Enterprise Task Text1 to Task ID and insert to my Project. I
select Published Fields in Tool > Customize and select Task ID for
publishing to Web. On PWA, I allow the Enterprise Task Text1 showed in
Timesheet View. But when I select Timesheet View, the column name of
Enterprise Task Text1 is not right (not Task ID), it show predefined column
name: Baseline Start, sometime it show Baseline Finish etc.
How to fix it?