Show final summary task different duration

T

tshad

I have most of my tasks showing the durations as Hours.

But I would like to also see my main summary task as days.

Is there a way to set that up for just that task?

Thanks,

Tom
 
M

Mike Glen

Hi Tom,

Welcome to this Microsoft Project newsgroup :)

Yes. First you need to run the Format_Duration macro from
Tools/Macro/Macros... to set all Durations to hours. Then set you
Tools/Options.../Schedule tab to give Duration in Days - that'll fix the
summaries. Then for each new task enter an h after each time as you enter
the Duration.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 