A
alppix
Is it possible to show lag time in the gantt chart? Or in own field?
(ms project 2003)
I know that I can see it from predecessors field, but I would like to
have it in own field or in gantt chart.
I was able to make own custom field which shows it somehow, but it
didn't work if task has more than one relation.. That own field just
had formula which collected character from wanted index in predecessor
field.. From that field I could show it in the gantt also.
So, is there any proper way to do this or does anyone know any good
formula how to get the information needed?
(ms project 2003)
I know that I can see it from predecessors field, but I would like to
have it in own field or in gantt chart.
I was able to make own custom field which shows it somehow, but it
didn't work if task has more than one relation.. That own field just
had formula which collected character from wanted index in predecessor
field.. From that field I could show it in the gantt also.
So, is there any proper way to do this or does anyone know any good
formula how to get the information needed?