The Gantt Chart is shows task related information. While you can show a
list of the resources assigned to a task, there is no way I know of to
show the over-allocation amount. However, you can easily show that in
the Resource Graph view (along with other resource-orientated views).
Not on the Gantt Chart. But you could use a split screen and open the
Resource Usage view in the bottom pane. Those resources overallocated will
appear in red.