M
Marcus Holmes
Hi All,
I have a bunch of tasks in my project (like 500) and a baseline that shows
the timeline and how long each task should take.
What I would like to see is one number that shows me what percentage
complete the entire project should have been at this date. I can figure
out how to show the percent complete, but how do I make it tell me how far
along I should be?
I tried the Slipping filter and that's good for showing percentage
complete per task, but not necessarily at the project level and showing
how much each task SHOULD BE completed.
Any ideas?
Thanks,
Marcus
I have a bunch of tasks in my project (like 500) and a baseline that shows
the timeline and how long each task should take.
What I would like to see is one number that shows me what percentage
complete the entire project should have been at this date. I can figure
out how to show the percent complete, but how do I make it tell me how far
along I should be?
I tried the Slipping filter and that's good for showing percentage
complete per task, but not necessarily at the project level and showing
how much each task SHOULD BE completed.
Any ideas?
Thanks,
Marcus