C
Colleen
I am creating a step-by-step training manual on how my team will access PWA
to enter their hours completed on their assigned tasks. I would like to know
if there is a way to automatically default display the "Show Scheduled Work"
option so that the "Work" row appears automatically along with the "Actual
Work" row. As of right now I know that by clicking on the "View Options"
button they can check "Show Scheduled Work" and it will then appear. But I
want to know how I can make this default for all Task views on PWA so that I
don't have to include this instruction in my manual to the team. Thanks, we
are currently running MS Project Server 2002 I believe.
Colleen
to enter their hours completed on their assigned tasks. I would like to know
if there is a way to automatically default display the "Show Scheduled Work"
option so that the "Work" row appears automatically along with the "Actual
Work" row. As of right now I know that by clicking on the "View Options"
button they can check "Show Scheduled Work" and it will then appear. But I
want to know how I can make this default for all Task views on PWA so that I
don't have to include this instruction in my manual to the team. Thanks, we
are currently running MS Project Server 2002 I believe.
Colleen