Show Scheduled Work to be default displayed in Tasks

C

Colleen

I am creating a step-by-step training manual on how my team will access PWA
to enter their hours completed on their assigned tasks. I would like to know
if there is a way to automatically default display the "Show Scheduled Work"
option so that the "Work" row appears automatically along with the "Actual
Work" row. As of right now I know that by clicking on the "View Options"
button they can check "Show Scheduled Work" and it will then appear. But I
want to know how I can make this default for all Task views on PWA so that I
don't have to include this instruction in my manual to the team. Thanks, we
are currently running MS Project Server 2002 I believe.

Colleen
 
D

Dale Howard [MVP]

Colleen --

I applaud you for creating a training manual for your team members on how to
enter progress properly in the View My Tasks page! Way to go, my friend.
:) To answer your question, there is no way to force this setting on every
team member's View My Tasks page. Instead, you must make this a training
and performance issue with them. Teach them to select this option, and then
hold them accountable for doing so. Just the fact that you are creating a
training manual for your team members should help with this issue. Hope
this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top