Q: I am trying to create a project view in PWA that shows start variance and
finish variance with traffic-light indicators. I have two questions.
1) Is there a way to show the standard Start Variance and Finish Variance
with graphical indicators?
2) If not, I have created two Enterprise Duration fields called "Start Var."
and "Finish Var." I set their values to equal Start Variance and Finish
Variance, respectively. But they do not get populated correctly. When I
show the Start Variance column and the Start Var. (Enteprise Duration1)
column side by side, on every detail line Start Variance has a value and
Start Var. says "#Error". What is going on and how can I fix it?
finish variance with traffic-light indicators. I have two questions.
1) Is there a way to show the standard Start Variance and Finish Variance
with graphical indicators?
2) If not, I have created two Enterprise Duration fields called "Start Var."
and "Finish Var." I set their values to equal Start Variance and Finish
Variance, respectively. But they do not get populated correctly. When I
show the Start Variance column and the Start Var. (Enteprise Duration1)
column side by side, on every detail line Start Variance has a value and
Start Var. says "#Error". What is going on and how can I fix it?