Show task duration in days (not hours) in Project Web Access

S

SteveGold

I am using Project Server 2003. The development resource go to Project Web
Access to see the tasks assigned to them.
In the "View My Tasks" view in PWA, the tasks are showing up in hours. I
would like these tasks to show up in days instead.
 
M

Marc Soester

Hi Steve,

Are you sure that Duration is hours ( not Work?). Usually duration can be
viewed in days and work in hours within PWA

Please let me know.
Thanks
 
S

SteveGold

Hi Mark,
The view I am referring to seems to be the default view when a resource goes
to "My Tasks" in PWA. It shows 3 fields that have time values: Work, Actual
Work and Remaining Work. All three of these fields show hours - I would like
them to show days instead.

Thanks,
-steve
 
M

Marc Soester

Hi Steve,

Sorry to say, but you cannot change them to days. Work is always displayed
in hours and duration in days. Sorry I wish there was a way to do this.
 