Show tasks slipping against dates given in a master schedule.

H

Heather020

Our Testing PM has a separate schedule that has only deliverable dates in my
master schedule as placeholders. The problem she is slipping on her
deliverable and wants HER plan to reflect this slippage.
I have baselined my schedule so it will show at the highest level that her
date is shifted but can she baseline her plan and print a view or report that
shows what are her issues that created this problem that feed into my one or
two lines in the Master.

Thanks all
 
C

Crook

Hi Heather020!

This sounds like a traditional reporting problem for the Testing PM and her
project. If she saved a baseline of her project plan at the beginning of
the project, then the report is relatively straight forward to make using
the tools available in ms project. But, if she did not save a baseline of
her project plan this will be a difficult task.