R
Rob
Hello All,
I have a question dealing with percentages for resources. Is there any way
on the resource usage and/or task usage to show the following:
1. What part of the project is assigned to the resource in percentage and
total numberof days/weeks/months etc.
2. What percentage of the the project does a specific task include. For
example if the project is ten days and a specific task is five days then that
task is fifty percent of the total projects' duration.
I am sure that there are fields that show this information in both the
resource usage and task usage but I can't find them. Any help would be
greatly appreciated.
Regards,
Rob
I have a question dealing with percentages for resources. Is there any way
on the resource usage and/or task usage to show the following:
1. What part of the project is assigned to the resource in percentage and
total numberof days/weeks/months etc.
2. What percentage of the the project does a specific task include. For
example if the project is ten days and a specific task is five days then that
task is fifty percent of the total projects' duration.
I am sure that there are fields that show this information in both the
resource usage and task usage but I can't find them. Any help would be
greatly appreciated.
Regards,
Rob