H
Helen
Hello,
I'm using Project 2002. I have some tasks, which I have assigned to a human
resource of 200%, ie I think I've given the tasks to two people, but do
correct me if I'm wrong. Each task, however, is only done by 100% of the
resource, ie one person. I have then levelled the tasks, and I want to colour
code the tasks to show which of the two people does which task so I can
easily glance at it and see. Anybody know how to do that?
Thanks
Helen
I'm using Project 2002. I have some tasks, which I have assigned to a human
resource of 200%, ie I think I've given the tasks to two people, but do
correct me if I'm wrong. Each task, however, is only done by 100% of the
resource, ie one person. I have then levelled the tasks, and I want to colour
code the tasks to show which of the two people does which task so I can
easily glance at it and see. Anybody know how to do that?
Thanks
Helen